Tracking schedule slips

Freeze the working schedule at two real moments, an initial proposal and a signed contract, then compare the live plan against sign-off to see exactly how far things have drifted.

What you'll achieve

Capture the agreed programme as a baseline, then compare later disruption against it in the project's own schedule.

You'll end up with: Two named baselines, Initial proposal and Agreed contract, with the live plan showing every day of drift against the contract point.

A programme moves through more than one moment worth keeping

Keep the project on track, step two: freeze the agreed programme so you can see what moves. A project's programme is never agreed once and then left alone. Riverside Apartments moves through a real sequence: a first proposal, a client-approved contract, then the everyday disruptions, a sick day here, a late client variation there, that push the live plan further from what was signed. Monument's schedule is versioned so you can freeze any of those moments and keep editing afterward without losing the ability to look back.

We'll save two baselines around a real sign-off, then let two later disruptions move the live plan, and finally compare it against the contract point to see the drift.

Two versions, one live and any number locked

The schedule only ever shows you one of two kinds of thing. The working version is the programme you actually edit, every stage you draw and every delay you insert lands here. A baseline is a frozen copy of it: the instant you save one, Monument snapshots the working version exactly as it stands and never lets it change again. That immutability is the entire point, a baseline you could still edit wouldn't be a promise, it would only be another draft.

Focus the project, then freeze the moment

Baselines are saved per project, so start by opening Riverside Apartments alone. Click the Open page icon on its row in the firm-wide schedule. The project page opens on its Schedule view, with every stage visible. Then open the version selector in the heading, which reads Working on the live plan.

  1. 1

    Click the Open page icon on the Riverside Apartments row. The project opens on its Schedule view.

  2. 2

    Open the version selector and choose Save as Baseline.

  3. 3

    Name it Initial proposal and confirm with Create baseline, before any client discussion changes the plan.

Let real disruption move the plan, then freeze the sign-off

With Initial proposal saved, client discussions add a review day to Concept Design. Open the stage's Delay control to insert the day, watch every later stage slide out to match, and save the working version. That's the moment the client actually signs off, so it becomes the second baseline.

  1. 1

    Open Concept Design, click Delay, then Apply to insert a review day and push the linked stages later.

  2. 2

    Save the revised programme.

  3. 3

    Open the version selector, choose Save as Baseline, and name this one Agreed contract.

Delivery doesn't stop being disruptive once the contract is signed. Staff sickness adds a day to Documentation, and a later client variation adds one more to Contract Administration. Both delays use the same Delay control on the stage, and both push the remaining programme further out. Save the working version again once they've landed, this live version, carrying both disruptions, is what gets compared against the contract.

Compare the live plan against what was signed

Comparing versions happens on the project itself, not the firm-wide schedule. Open Riverside Apartments and switch to its Schedule view. A project that is under way opens on Progress, so you may need to switch. Use Compare version… there to stack Agreed contract underneath the live plan.

  1. 1

    Open Riverside Apartments and switch to its Schedule view.

  2. 2

    Click Compare version… and choose Agreed contract.

  3. 3

    Agreed contract appears read-only beneath the live plan, on the same dates across the top.

Both timelines share the same dates, so anything that's moved since sign-off, Documentation's extra day, Contract Administration's slip, shows up as the visible gap between the two rows rather than something you have to hunt for.

One active baseline drives the Gantt and the fee variance

Saving a baseline also makes it the project's active comparison baseline — the one Monument uses everywhere a single point of comparison is needed, not just in Compare version. Saving Agreed contract made it active automatically; Initial proposal is still there to compare against whenever you choose it instead.

That one active baseline drives two surfaces at once:

  • On the schedule, the Original start, Original finish and Days moved columns in the Columns menu show each task's baseline dates and exactly how many days it has moved.
  • On the project page, the baseline fee variance compares each stage's fee at the active baseline against its current fee, side by side, with the dollar and percentage change.

Switching which baseline is active, on the project page's comparison picker, changes both of those at once. Older baselines don't disappear: they stay saved as versions, and picking one makes it the active comparison again.

Troubleshooting

  • The timeline won't respond to a drag. You're viewing a baseline inside the version selector, not the working version. Choose Return to working version and editing comes back.
  • Compare version has nothing to offer. It lists saved versions other than the active and working versions. If a project has none yet, save a baseline first.
  • A baseline looks stale next to the current plan. That's expected, baselines never update themselves. If the agreed plan genuinely changes again, take a new baseline rather than expecting an old one to move with it.
  • The fee variance jumped after saving a new baseline. A new baseline becomes the active comparison automatically, so the variance now compares against it instead of the older one. Pick the older baseline again on the project page if that's the comparison you wanted.

You'll know it worked when you can name each stage's slip since the client signed.

Where this fits next

Next, read the reports on a project. See critical path and automatic dates for what the baseline columns and the rest of the Gantt overlay show.